After reviewing the Week 3 Lesson Video for Getta Byte Software, write and submit a one- to two-page paper on what Ima Payne, the project manager at Getta Byte Software, put together for her preliminary project schedule. Address the following questions.
- What types of information have we learned about the Getta Bill project by reviewing the project schedule and all the information used to generate it?
- If Ima made the decision to try to use the Agile Methodology for the Getta Bill project, what should she do?
- How could the WBS help the next step to plan using Agile?
Transcript of their discussion
Getta Byte Software
The WBS and Schedule
Time to create a WBS for the the billing project.
Hmm…
What are the major tasks?
We decided to purchase BillRite software.
I know the milestones.
- Finalize requirements
- Purchase software
- Customize software
- Transfer data to cloud
- Train personnel
- Go live
I need to add detail or subtasks.
Finalize Requirements
- Gather requirements from users.
- Gather requirements from customers.
Purchase Software
- Select vendor.
- Negotiate contract.
- Execute purchase.
Customize Software
- Define features.
- Set up test environment.
- Develop customization.
- Test customization.
Transfer data to cloud
- Validate data.
- Map fields.
- Transfer data.
Train Personnel
- Develop training with vendor.
- Schedule training for CSRs.
- Conduct training.
Go Live
- Release system into production.
Well! Let’s see what that looks like in a schedule.
Getta Byte Schedule
Wow! We have to get started so we can make the September 1 deadline.
Getta Byte Software
The End.